Renovation Buitenveldertselaan 148, Amsterdam

Category:Sustainability, Office, Retail
Client:Kroonenberg Groep
Location:Amsterdam
Construction Costs:Available upon request
Architect:Dam & Partners Architects

Project Description

The renovation project at Buitenveldertselaan 148 in Amsterdam involves the transformation and addition of floors to the existing building, which consists of a basement and four floors with a total gross floor area of approximately 4,750 m²

Construction and Interior Design

The ground floor is designated for retail, while the upper floors accommodate office functions. With the addition of an extra floor and the completely renovated façade, the building is almost unrecognizable. The shell has been largely preserved, but due to the reconfiguration and new installations, the building is now future-proof and has an impressive appearance.

The new façade is constructed with wood-steel-concrete (WSC) elements combined with large aluminum retro window frames with divided lights. The design features extensive use of glass, light gray granite bands at the level of the floors, and dark ceramic tiles, contributing to a modern, corporate appearance. The new roof extension is slightly set back from the façade line, and a rooftop terrace has been created with views of the greenest part of Amsterdam.

The building consists of six floors. A store of approximately 960 m² will open on the ground floor and in the basement, while the four upper floors together offer about 3,170 m² of office space. The store opened in December 2023, and the offices were completed in the spring of 2024.

Enhancement of sustainability

With approximately 150 solar panels on the roof, the building generates a significant amount of green energy, contributing to a reduced ecological footprint. The use of triple glazing provides excellent insulation, resulting in an energy label of A+++.

The building is connected to district heating, which reduces reliance on fossil fuels. The advanced ventilation system is equipped with heat recovery, further enhancing energy efficiency. Additionally, the property is fitted with LED lighting, which ensures lower energy consumption and a longer lifespan for the lighting.

The building is equipped with a smart and sustainable Building Management System (BMS) from Sense, which ensures efficient control of the climate system. Basic electrical systems and empty data connections have been strategically placed in wall conduits to ensure flexibility in layout. Additionally, a state-of-the-art climate installation has been implemented, contributing to an optimal indoor climate

These sustainable features do not only create an energy-efficient building but also a comfortable and attractive working environment

Factsheet

  • Total area: 4,750 m² GFA
  • Duration: 17 months

Project Duration

  • Start of the Technical Design phase: March 2022v
  • Start of the implementation phase: November 2022
  • Completion: March 2024